Home / Guides / Subcontracting plans

Guide

Subcontracting plans,
and reporting against them

The plan is the easy part. Reporting participation accurately against it, period after period, is where the effort actually goes, and it depends entirely on what was captured when each award was placed.

Plan floor raised to $900,000Capture classification at award
QUICK ANSWER
Planvs report
Goals are easy; accurate reporting is the work
Three conditions decide when a plan is required
Classify suppliers at award, not at period close
Evidence good-faith effort on the awards themselves
DIRECT ANSWERChecked August 2026

A small business subcontracting plan sets out the goals a prime contractor commits to for subcontracting with small and other designated business categories, together with how it will pursue and report against them. Plans are generally required on contracts expected to exceed the threshold at FAR 19.702, raised to $900,000 in the October 2025 adjustment, where subcontracting opportunities exist.

When a plan is required

Three conditions, checked together

Contractors sometimes assume the threshold alone decides it. Subcontracting opportunity and the nature of the contract both matter.

Guides • Walkthrough

Three conditions, checked together

Contractors sometimes assume the threshold alone decides it. Subcontracting opportunity and the nature of the contract both matter.

  • Value above the FAR 19.702 threshold
  • Meaningful subcontracting opportunity
  • Prime is not a small business
THREE CONDITIONSCHECKED TOGETHER
01 · VALUE THRESHOLD
Above FAR 19.702
$900K
Raised from $750,000 effective 1 Oct 2025.
02 · OPPORTUNITY
Meaningful subcontracting
03 · PRIME SIZE
Not a small business
ConditionWhat it means
The value thresholdPlans are generally required where the contract is expected to exceed the threshold at FAR 19.702, raised from $750,000 to $900,000 effective 1 October 2025
Subcontracting opportunities existWhere a contract offers no meaningful subcontracting opportunity, the requirement can fall away. That determination should be documented rather than assumed
The contractor is not a small businessSmall business primes are generally not required to submit a plan, though they may still face expectations from their own customers
Confirm against your contractRequirements can be specific to the acquisition, so the contract itself is the authority rather than general practice
Where subcontracting plans get difficult

It is the reporting, not the plan

Writing goals takes an afternoon. Reporting against them accurately, every period, is the part that consumes teams.

Book a demo
Guides • Walkthrough

It is the reporting, not the plan

Writing goals takes an afternoon. Reporting against them accurately, every period, is the part that consumes teams.

  • Classify suppliers at award
  • Watch goals mid-period
  • Keep reported totals traceable
REPORTING · PERIOD CLOSE
Where the work piles up
HARD PART
Writing goals
An afternoon — not where teams struggle
Classify at award
Turns reporting from research into a filter
Watch goals mid-period
A gap in month two can still be fixed
Keep totals traceable
Break down to awards with evidence attached
Accurate reporting every period is what consumes teams.
ProcureAudit Inferred at reporting
The challenge

Inferred at reporting

Supplier categories are worked out at reporting time from names and invoices, which is slow, partly accurate and hard to verify.

CapturedAfterwards
AccuracyPartial
VerifiableWeakly
ProcureAudit Recorded at award
With ProcureAudit

Recorded at award

The person placing the award records the classification when they select the supplier, which is when certainty is highest.

CapturedAt award
AccuracyHigh
VerifiableYes
ProcureAudit Compared at period end
The challenge

Compared at period end

Committed goals are compared against actuals only once the period closes, which is exactly when nothing can be done about a shortfall.

ComparedAt close
ActionImpossible
OutcomeAn explanation
ProcureAudit Tracked throughout
With ProcureAudit

Tracked throughout

The gap between commitment and actual is visible at any point, so a shortfall in month two is still something you can address.

ComparedContinuously
ActionPossible
OutcomeA correction
ProcureAudit Asserted
The challenge

Asserted

The file states that reasonable efforts were made to find small business sources without showing what those efforts were.

ShownNo
EvidenceAbsent
WeightLow
ProcureAudit Evidenced in the records
With ProcureAudit

Evidenced in the records

Sources sought, outreach undertaken and the reasons awards went where they did are recorded on the awards themselves.

ShownYes
EvidenceOn the awards
WeightHigh
ProcureAudit An assembly exercise
The challenge

An assembly exercise

Pulling awards from several places, matching suppliers to categories and totalling, most of which is data work rather than reporting.

EffortWeeks
RepeatablePainfully
ConfidenceModerate
ProcureAudit A filter and an export
With ProcureAudit

A filter and an export

Awards already carry classification, value and date, so the report derives from records rather than being constructed.

EffortHours
RepeatableEasily
ConfidenceHigh
What each award should carry

Five fields that make reporting a filter

FieldWhy it matters
Supplier classificationRecorded at award by the person who selected the supplier, rather than inferred from a name later
Award valueThe figure participation is calculated against, held on the record rather than pulled from invoices
Award dateWhich reporting period the award falls into, determined by the record rather than by a later judgement
Sourcing effortWhat was done to find sources in the relevant categories, which is what evidences good faith effort
Supporting evidenceAttached to the award, so a reported total can be broken down to the individual awards behind it

The plan floor and related figures are adjusted periodically. Confirm the current threshold at FAR 19.702 before relying on it.

FAQ

Common questions about subcontracting plans

When is a subcontracting plan required?
Generally where the contract is expected to exceed the threshold at FAR 19.702, raised from $750,000 to $900,000 effective 1 October 2025, subcontracting opportunities exist, and the prime is not a small business. Confirm against your own contract.
Did the threshold change recently?
Yes. The plan floor moved from $750,000 to $900,000 in the same inflation adjustment that raised the micro-purchase and simplified acquisition thresholds, effective 1 October 2025.
Are the goals guarantees?
No. They are commitments to make good faith efforts. That is why evidence of what you actually did to find sources matters as much as the final percentages.
How do we evidence good faith effort?
Through records of sources sought, outreach undertaken and the reasons awards went where they did, kept on the awards themselves rather than summarised at reporting time.
Why does classification need to be captured at award?
Because the person placing the award knows with certainty at that moment. Reconstructing categories later from supplier names and invoices is where most of the effort and most of the error comes from.
What if we are going to miss a goal?
Seeing it while the period is still open is what matters. A gap identified in month two can be addressed through sourcing decisions. The same gap at period close can only be explained.
Do small business primes need a plan?
Generally not, though customers can still have expectations and prime contracts can impose their own requirements. The contract is the authority.
Related reading

Other explainers and the pages they connect to

ProcureAudit Small business liaison officers
RESOURCE

Small business liaison officers

Participation evidenced from award records rather than estimated.

Learn more
ProcureAudit Purchase thresholds
RESOURCE

Purchase thresholds

The figures adjusted in the same October 2025 change.

Learn more
ProcureAudit FAR Part 44
RESOURCE

FAR Part 44

Subcontracting policies, consent and purchasing system reviews.

Learn more

Bring your last participation report

We will show what producing it from award records would look like, and how much of it was reconstruction.

Book a demo